Oct. 2, 2006
CDM Inc., in partnership with Carollo Engineers, has been awarded a contract by the Greater Cincinnati Water Works (GCWW) to design and construct a 240-million-gallon-per-day (mgd), potable water ultraviolet light (UV) disinfection facility. The $14 million project, one of the largest UV disinfection systems for drinking water in the United States, will improve public health protection while keeping GCWW in the vanguard of the nation's water purveyors...

Ultraviolet light disinfection at 240-mgd facility will serve Cincinnati, OH, customers

CINCINNATI, OH, Oct. 2, 2006 -- CDM Inc., in partnership with Carollo Engineers, has been awarded a contract by the Greater Cincinnati Water Works (GCWW) to design and construct a 240-million-gallon-per-day (mgd), potable water ultraviolet light (UV) disinfection facility. The $14 million project, one of the largest UV disinfection systems for drinking water in the United States, will improve public health protection while keeping GCWW in the vanguard of the nation's water purveyors.

The new UV facility will be built at the Richard Miller treatment plant, a surface water plant that employs conventional surface water filtration, along with post-filtration granular activated carbon (GAC) adsorption for organics removal. The UV disinfection process will be installed between the GAC effluent and the finished water clearwells prior to addition of chlorine and corrosion control chemicals. UV plus chlorine will provide a multiple disinfection barrier for inactivating a variety of microbes, significantly improving public health protection.

This project includes a program to test and validate UV reactor performance onsite following design and construction of a new UV building. Following the pre-qualification of UV equipment vendors, a full-scale demonstration study will be conducted for approximately 12 months. The demonstration facility will be constructed to house one or two fully operational UV test trains, each rated at a design capacity between 25 and 60 mgd. Following onsite reactor validation and selection, the remaining UV reactor trains will be installed in the UV building under a second construction phase. The facility is scheduled to be commissioned and operational in 2011.

With headquarters in Cambridge, MA, CDM Inc. (www.cdm.com) is a consulting, engineering, construction, and operations firm delivering exceptional service to public and private clients worldwide. It employs more than 3,600 people.

Also see:
-- "CDM completes water supply well for Navajo Nation"
-- "CDM participates in U.S. Mayors Conference on climate change"
-- "CDM workshop at IWA Congress forecasts future of water industry"

###

Sponsored Recommendations

ArmorBlock 5000: Boost Automation Efficiency

April 25, 2024
Discover the transformative benefits of leveraging a scalable On-Machine I/O to improve flexibility, enhance reliability and streamline operations.

Rising Cyber Threats and the Impact on Risk and Resiliency Operations

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

State of Smart Manufacturing Report Series

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

SmartSights WIN-911 Alarm Notification Software Enables Faster Response

March 15, 2024
Alarm notification software enables faster response for customers, keeping production on track