City extends sewer main with pressure jacking pipes

Dec. 21, 2008
Environmental aspects and future-oriented thinking lead the municipality of Groningen in the Netherlands to extending their existing sewer main sized DN 1000 and DN 1200...

Environmental aspects and future-oriented thinking lead the municipality of Groningen in the Netherlands to extending their existing sewer main sized DN 1000 and DN 1200. The gravity sewer main could not cope with high flow rates occurring during heavy rainfall. To prevent sewage from overflowing and polluting nature the authorities decided to convert it into a closed pressure system. With this and its extension by 2.4 km HOBAS CC-GRP Sewer Systems a capacity of 3000 m³/h will be achieved so that the line would easily cope with future needs as well as the connection of a further village.

The former gravity sewer main was converted it into a closed pressure system to prevent overflows and pollution.Preparations for the project were made in 2004. Since the line crosses a busy part of the town Groningen HOBAS proposed the utilization of CC-GRP Pressure Pipe Systems which can be installed by open as well as trenchless construction. Being the only supplier of GRP pressure pipes which can also be jacked the local engineers decided for HOBAS CC-GRP placing an order worth 1.222.000 Euros for the complete line. This included 5 jacking sections with HOBAS CC-GRP Jacking Pipes DN 1000 to 1500 and Pressure Pipes PN 6, DN 1000 and 1600 m DN 1200 as well as flanges, elbows, reducers and tees with stainless steel locked joints. Five different contractors were assigned to complete the job and a sixth will rehabilitate the pumping station in two years.

Several obstacles along the pipe route, such as roads and a channel, were overcome by microtunneling.Several obstacles along the pipe route, such as roads and a channel, were overcome by microtunneling. Due to the requirements by the road authorities two jacking sections running beneath the highway were realized with cover pipes, which were also delivered by HOBAS Benelux, the HOBAS CC-GRP Pressure Pipes were consequently inserted. The largest with an outer diameter of 1500 mm was utilized beneath highway A7.

The three other microtunneling sections were implemented with in this field unique CC-GRP pressure jacking pipes PN 6 and flush FWC couplings. These run beneath a gas pipeline, a main road, several streets and a navigable channel where the installation was conducted in 12 m depth. A 275 m long section with CC-GRP pressure jacking pipes of 1280 mm outer diameter was jacked in a curve radius of 1300 m. The contractor decided to install an intermediate station which according to safety standards is required for jacking with over 4000 kN. Due to the smooth and non-absorbing outer surface of HOBAS Pipes their light weight and constant outer diameter, the maximal jacking force did not exceed 1800 kN. The intermediate station was therefore never in operation.

The HOBAS flush couplings utilized for jacking are absolutely leak tight and facilitate assembly.Thanks to innovative HOBAS CC-GRP Pipe Systems and the constant support of HOBAS Experts, all involved parties look back to a smooth and unobstructed implementation, Groningen is prepared for future needs and Mother Nature can breathe a sigh of relief.

December 2008

###

Sponsored Recommendations

ArmorBlock 5000: Boost Automation Efficiency

April 25, 2024
Discover the transformative benefits of leveraging a scalable On-Machine I/O to improve flexibility, enhance reliability and streamline operations.

Rising Cyber Threats and the Impact on Risk and Resiliency Operations

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

State of Smart Manufacturing Report Series

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

SmartSights WIN-911 Alarm Notification Software Enables Faster Response

March 15, 2024
Alarm notification software enables faster response for customers, keeping production on track