“I welcome news that the long-awaited water and sewer infrastructure upgrade project in Northeast Queens is now complete,” said Assembly Member Edward C. Braunstein. “These upgrades will serve to help relieve local flooding issues and provide more reliable water service to residents in Bayside, Auburndale and Flushing. I want to thank NYC DDC, DEP and DOT for their hard work and collaboration to see this important project through.”
In addition to water mains, nearly two miles (9,985 feet) of storm, sanitary and combined sewers were replaced and 23 new catch basins were added in the project area to improve stormwater drainage.
As part of the final street restoration, 19,210 feet of new curbs were added the project area and 8,200 feet of old curbs, 432,000 square feet of asphalt and 82,800 square feet of concrete sidewalks were replaced.
To span the Clearview Expressway, the project used micro-tunneling techniques to build three small new tunnels for water, sewer and private utilities under the highway from east to west at 38th Avenue.
The project was designed by DDC’s in-house design team. Construction was completed by C.A.C. Industries Inc. and engineering services were provided by Entech Mirabal Engineers PLLC.