Completed structure after application of 125 mils of Raven 400S 100% solids epoxy coating.
Click here to enlarge imageThe dynamic population growth experienced in the area prompted the City of Fresno to pursue extensive capital improvements, including a two-phased expansion of the plant. In the fall of 1996, the plant completed its first-phase expansion which included replacement of the old headworks. Depending on growth, the state-of-the-art facility was designed to serve area needs for 40 to 50 years.
But after only eight years, a devastating corrosion problem was destroying the relatively new structure. Due to inadequate initial corrosion protection, approximately 50,000 square feet of various headworks chambers and troughs were severely deteriorated from exposure to hydrogen sulfide induced corrosion.
Although the entire structure had been coated with a qualified coating from a major manufacturer when new, the coating was applied too thin to deliver monolithic status - “a barrier without fault” - and post application inspections evidently failed to identify this inadequacy. A mere eight years later, this oversight had resulted in a one to three inch deterioration of the concrete surfaces inside the multi-chambered structure; exposing damaged rebar in some areas and rough aggregate throughout the top of the structures. The structural integrity of some of the steel gates between chambers was also compromised due to severe corrosion on both sides of the walls. The potential for catastrophic failure was imminent in many upper areas of the facility.
“It was our assertion that the original protective coating was applied improperly and ultimately failed,” said Saeid Vaziry, P.E., Chief of Technical Services for the City of Fresno Public Utilities Department. “The corrosion was extensive and if we did not act quickly, we believed the damage would be irreversible.”
Rehab Solutions
The eight headworks chambers and troughs were integrally constructed within the structure, all above grade and aesthetically designed. Construction of a new structure was financially out of the question.
A thorough inspection of the deteriorated structure determined the structures were still sound and salvageable if an appropriate structurally enhancing technology was used. The owner therefore decided to use a “structural protective coating system” to rehabilitate the headworks. Emergency funding was sought and approved.
A thorough review of products and applicators with proven rehabilitation success in similar environments was also conducted. The city selected Raven 400S 100% solids epoxy to restore the flow-split unit. Spinello Companies was chosen as the general contractor to perform general repairs, and provide flow bypass. The contractor then entrusted F&L Concrete Services to apply the protective coating. The city provided construction and project management services.
Bypass Requirements