Figure 1. The Antipolo network system comprises three stages of pumping stations located at Kingsville, Siruna and Lucban, and two reservoirs at Siruna and Lucban.
Click here to enlarge imageIn order to optimize the Antipolo Water Supply System, Manila Water's plan was to incorporate the anticipated rapid growth of the area from a current population of 656,000 people to 2.2 million by 2022. The utility also planned to evaluate the steady state and transient hydraulics of the preferred pipeline, pump station and reservoir combination, and to improve the overall reliability and efficiency of the Antipolo network system.
Challenges
This project presented many challenges. First, the suction line had limited capacity, which hindered maximization of the output of the first pumping station in Kingsville. The hilly terrain of the Antipolo area presented another major difficulty. Previous efforts to overcome this challenge were made by maintaining high pressure heads at the pumping stations, but the extreme differences in elevation created intensively high pressure heads in the low-lying areas, resulting in pipe breakages.
Frequent power failures, creating sudden shifts in pumping operations, presented yet another challenge (see Fig. 2). And finally, communities in the area comprised mostly low income families who got their water supply from shallow wells, private deep wells and water delivery trucks. These methods are extremely expensive and also expose the families to low water quality, which may impose health risks.
To overcome these challenges, a hydraulic model of the Antipolo water system was created. Hydraulic and transient simulations were conducted to analyze network constraints and to identify possible solutions to improve the performance of the Antipolo network. Based on the simulations and intensive field investigation, network improvement projects were conceptualized, designed and implemented.
Water modeling plan
First, the hydraulic network model was calibrated in WaterGEMS V8 XM Edition, based both on field data and the existing network database. Hydraulic and transient simulations using WaterGEMS and HAMMER helped identify critical locations in the system.
The primary reliability strategy for this project was to subdivide the water distribution network into four separate pressure zones: the Unboosted Zone, the Siruna Pressure Zone, the Lucban Pressure Zone and the Lucban Pump Zone (see Fig. 3).
Since the Unboosted Zone had constraints in maximizing the output of the water system, a parallel line coming from the Siruna Pressure Zone was installed to cover some areas of the Unboosted Zone. The strategy was to minimize the area covered by the Unboosted Zone. Smaller pressure zones were then designed by creating smaller reservoirs in areas of rolling terrain to break pressure surges due to extreme differences in elevation, and to ensure water availability regardless of interruptions in pumping operations.