Project Profile: Ground Penetrating Radar Used in Investigation of Tunnel Deterioration

Just a few years after the opening of the Cumberland Gap Tunnel, a mountain tunnel that links Kentucky and Tennessee along US Route 25E, highway officials noticed moderate to severe settling of the continuously reinforced concrete pavement, with many voids discovered beneath the pavementsurface. The Kentucky Transportation Center brought in a research team to find the root causes of the settlement issues by using ground penetrating radar (GPR) and hydro-geochemical water testing (HGWT). The use of the GPR equipment, manufactured by Geophysical Survey Systems Inc., provided information that slashed the costs for the tunnel repair project by showing more precisely where repairs were necessary. The equipment is now an integral part of the long-term inspection process that will assist in finding other distressed areas within the tunnel if they arise in the future.

Master everything from OSHA regulations, to high-tech safety equipment in this FREE Special Report: Construction Safety Topics That Can Save Lives. Download it now!

Tunnel Through the Mountain Connects Kentucky and Tennessee
The Cumberland Gap Tunnel is a twin-bore mountain tunnel in the Appalachian Mountains, which goes through the picturesque Cumberland Gap—the first great gateway to the West. Constructed in 1996 at a cost of $260 million, the tunnel is located within the Cumberland Gap National Historic Park on the Kentucky-Tennessee state line. An existing narrow, winding, and somewhat hazardous two-lane road goes up and over the mountain, and the state decided to build the four-lane tunnel through the park and the mountain to improve traffic safety without interfering with the scenery.

Located about 1,000 feet below the pinnacle, the tunnel carries about 22,500 vehicles bi-directionally per day. About 10% of the traffic is trucks, predominately transporting coal from mines in Kentucky to fuel a Tennessee power plant.

Not more than four years after the tunnel opened, highway officials noticed a settlement area and an odd dipping of pavement. The steel-reinforced concrete pavement had settled in various areas of both the north and southbound tunnels. By 10 years after the tunnel’s completion, approximately 7,400 total square feet of pavement surface had voids beneath it that ranged from 0.5–40 inches deep. Only the steel reinforcement was keeping the pavement from collapsing.

Add Grading & Excavation Contractor Weekly to  your newsletter preferences and keep up with the latest articles on grading and excavation: construction equipment, insurance, materials, safety, software, and trucks and trailers.    

Investigation Uses GPR and Chemical Testing to Probe the Cause of Voids
The state made several attempts to shore up the settled pavement areas before initiating an investigative repair in 2007 that attempted to repair the most severely damaged section and get to the root of the causes of the settlement issues.

The effort was led by a team from the University of Kentucky College of Engineering Kentucky Transportation Center. The center is contracted to perform the Kentucky Transportation Cabinet’s investigative research tasks for highways, roads, and bridges.

Led by Brad Rister, senior research engineer, the research began with an analysis of the economic impact to the traveling public if the pavement was to fail and the tunnel had to be closed. The study showed that if they could no longer transport coal through the tunnel and had to find an alternate route, there would be about a four-hour diversion. User costs for that diversion, along with costs associated with delays for people living in Kentucky but commuting to work in Tennessee, amounted to about $1.1 million per day.

Based on the high level of economic impact, the state made the decision to find a permanent fix for the problem. But first they had to locate the voids and determine why the concrete pavement had settled in various areas throughout the tunnel. To do so, the research team performed GPR surveys and HGWT.

The tunnel was constructed with a 4–6 foot layer of crushed limestone-based material placed beneath the concrete pavement. By design, between 500,000–1.2 million gallons of groundwater flows beneath the tunnels on any given day through the 4–6 foot layer of crushed limestone. The HGWT testing showed that the groundwater inflow in certain areas is aggressive to calcite, so the calcium-rich limestone backfill material placed beneath the concrete pavement was dissolving and leaving the tunnel through the groundwater collection system every day. Laboratory tests confirmed that water samples with a calcium deficiency of less than 0.10 will start to dissolve limestone material. Some of the groundwater entering the tunnel was runoff from coal seams; when water runs through coal it changes chemical properties, becoming more acidic.

The testing results indicated that approximately 0.75–1.5 cubic yards of limestone sub-base material left the tunnel every month due to calcium-deficient groundwater beneath it. “That’s about a wheelbarrow and a half of material leaving the tunnel in solution, dissolving and washing out through drainage every day,” says Rister. This led to about 70–150 square surface feet of new void area opening up beneath the concrete pavement every month.

The team then used GPR technology developed by Geophysical Survey Systems Inc. to identify the location and size of the voids or cavities. The equipment, SIR-20 and SIR-3000 control units with a 900-MHz antenna and survey wheel, was used to scan from one end of the tunnel to the other on both tunnels, on 2-foot centerlines. Initially they pulled the antenna by walking, but as they grew more experienced, they progressed to attaching the equipment to a vehicle. Each side of the 4,600-foot tunnel takes about four to five hours to scan, or about 10 hours total.

The first void they found was 4 feet deep and 30 feet long; some of the void areas span across both lanes (30 feet wide) and extend from 1–70 feet in length.

“The concrete pavement was essentially performing as a bridge in these void locations,” says Rister. “Structural loading calculations indicate that a concrete slab if designed as a bridge would only be able to span 6 feet before starting to fail. The only reason the pavement structure did not completely collapse is because reinforcing steel is placed inside the concrete.”

According to Rister, the GPR equipment was able to delineate where the problems were and gave the team a way to continue to track the problem. They had originally started using the GPR technology in 2002 to conduct scans every six months to identify areas where new voids were appearing. Several costly but temporary fixes had been performed that involved digging a hole and backfilling it with concrete to support the structure. “GPR gave us a visual on where the problems were located,” says Rister. “It was such a large area that I don’t know what else we could have done to visually see where the problems were.”

Credit: GSSI
Groundwater inflow

The study determined that the best remediation strategy was to remove the existing limestone sub-base material and replace it with layers of crushed granite, separated by a geo-grid fabric, and a new 10-inch reinforced concrete pavement. Granite is inert and has properties not affected by the low-pH water.

Rister explains that the mountain through which the tunnel goes is a thrust fault—the bottom is limestone, then there is a layer of sandstone and then fieldstone. In Tennessee, the water runs through limestone, while the water coming in from Kentucky was running through fieldstone, so it didn’t have calcium elements. Groundwater with no calcium to neutralize the acid was what dissolved the limestone fill in the tunnel. “Being able to confirm the geologic formation gave us confidence that there were no voids that needed to be fixed on one end of the tunnel, significantly reducing repair costs.”

The initial proposal was to replace approximately 2,800 feet of pavement in each tunnel at an approximate cost of $10 million. The GPR and HGWT results, however, allowed crews to limit repairs to the isolated areas and save considerably. Completed in 2012, the project cost around $3 million. The project took 35 days, with work done 24 hours a day.

As part of the tunnel’s routine maintenance sequence, scans will be performed with the GPR every six months. The equipment is a key component of a long-term inspection process that will assist in finding other distressed areas within the tunnel if they arise in the future.

The project was selected for inclusion in the American Association of State Highway and Transportation Officials (AASHTO) 2012 High Value Research compendium, Research Impacts: Better–Cheaper–Faster. It was also featured in the National Cooperative Highway Research Program (NCHRP) executive brochure Research Makes the Difference, 2012.

According to Rister, whose group performs forensics work on failures of bridges, tunnels, and roads, GPR is an important tool available to obtain discernable information, providing an understanding of whether the problem is a sinkhole or settling pavement, and if the cause is water trapped beneath a roadway. “Our success goes back to use of the GPR,” explains Rister. “Without it we wouldn’t have had the ability to image what’s going on beneath the surface.”

About the Author

Gabriel Dadi, Clark Graves, & Roger Roberts,

Gabriel Dadi, Ph.D., P.E., LEED AP, is an assistant professor of civil engineering at the University of Kentucky, College of Engineering. Clark Graves, Ph.D., is associate director of the Kentucky Transportation Center in Lexington, KY. Roger Roberts, Ph.D., is a senior software engineer for Geophysical Survey Systems Inc.

Sponsored Recommendations

ArmorBlock 5000: Boost Automation Efficiency

April 25, 2024
Discover the transformative benefits of leveraging a scalable On-Machine I/O to improve flexibility, enhance reliability and streamline operations.

Rising Cyber Threats and the Impact on Risk and Resiliency Operations

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

State of Smart Manufacturing Report Series

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

SmartSights WIN-911 Alarm Notification Software Enables Faster Response

March 15, 2024
Alarm notification software enables faster response for customers, keeping production on track