Grand Rapids is developing a concrete asset management program to help extend the useful lifespan of its facilities.
Click here to enlarge imageThe appropriate construction materials specific to the project were evaluated and selected. Concrete designed specifically for repairs was used to address the concrete deterioration of the tanks. Waterproofing products such as new caulk and coatings were applied to protect the concrete and tunnels below the walkways. The repairs were completed during the summer months, when temperature and weather conditions were more favorable.
The restoration project included many operational considerations that were identified in the contract documents as WWTP flows could not be halted for long durations during the construction phase. Plant flows were diverted from two chambers in the tanks at one time and required that repairs be completed in a two-week period. To complete repairs in this short time, engineering considerations were made for the repair design and materials selection. The contractor’s construction schedule and repair process was also carefully planned.
“One of our biggest challenges during the restoration process was identifying ways to avoid disruptions to normal plant operations,” said Fisher. “We solved this by shutting down two tanks simultaneously, allowing us to retrain the necessary flow capacity for the other tanks at the plant.”
Another challenge for the contractor was embedded conduits in the concrete slab. An electrical sub-contractor was on site during the majority of the demolition to repair and provide temporary power to the process equipment, since conduits were exposed or damaged. Other operational considerations included the protection of process equipment that remained in service as restoration took place directly adjacent to the equipment.
These projects merely scratch the surface of the extensive work performed at the city of Grand Rapids Wastewater Treatment Plant. The close working relationship between the city, the Environmental Services Department and Walker Restoration enabled these projects to be completed in a successful manner. The Grand Rapids Wastewater Treatment Plant is developing a concrete asset management program which will result in better maintained concrete structures and an extended useful lifespan resulting in greater process reliability.
“Concrete restoration is helping the City of Grand Rapids to extend the lives of our concrete assets,” said Fisher. “The most impressive aspect of the restoration program has been the city’s ability to remain fiscally responsible to our taxpayers by maintaining control over the costs needed to fund these types of projects.”
About the Author:
Andrew J. Vidor is a design engineer for Walker Restoration Consultants, which provides specialized consulting, engineering, and restoration and preservation strategies and services. Its services include investigations, assessments, repair design, and capital-improvement/protection programs. For more information, visit the company’s Web site at www.walkerrestoration.com.