Wastewater project in Warsaw reaches milestone with completion of pipe jacking

April 30, 2011
WARSAW, Poland, Apr. 30, 2011 -- The underground connection to the new Czajka wastewater treatment plant in Warsaw, Poland, has been completed...

Fig. 1. Ready to go: the Herrenknecht AVND2400AB for the underground connection of a new wastewater treatment plant in Warsaw, Poland.

WARSAW, Poland, Apr. 6, 2011 -- The underground connection to the new Czajka wastewater treatment plant in Warsaw, Poland, has been completed. When finished, the state-of-the-art wastewater treatment system will treat the wastewater produced by 80 percent of the city's residents, improving the quality of water and life along the banks of the Vistula River.

Hydrobudowa 9 S.A., PRG Metro Sp.z.o.o. and KWG (PBG Group) have been commissioned to connect the plant with the underground wastewater network.

The Polish contractors selected the pipe jacking method for their tunnel project. Two Herrenknecht AVND micromachines were used for the difficult drives totaling 5,860 meters. Despite extraordinarily large diameters of 3 meters, depths of 10 to 14 meters, and extreme winter conditions, the Herrenknecht machines achieved performances of up to 36 meters a day.

Fig. 2. The jobsite teams realized in total 16 tunnel sections with lengths up to 930 meters with pipe jacking.Another challenge was presented by the high groundwater level, which in some places reached up to 8 meters above the top of the pipes. Because of this, the site teams had to dewater and seal the requisite construction shafts prior to tunneling. The Herrenknecht AVND pipe jacking machines, where required, are able to secure the tunnel face using a support fluid (bentonite and water mixture) and an additional compressed air cushion in the split excavation chamber, allowing safe tunneling under water pressure.

The separation of excavated solids from fluids was done utilizing the Herrenknecht Separation Plant HSP500, providing a capacity of 400 to 500 m³/h depending on the particle size distribution.

During the frigid winter months of 2010, the site team continued tunneling work, completing a total of 16 drives, some with short distances of about 80 meters and some with long-distance sections of 800 meters and more.

Fig. 3. To connect the sewer system with the Czajka wastewater treatment plant, the Herrenknecht Mixshield S-642 (Ø 5.35m) will be used for the 1,300m long Vistula River Crossing tunnel.The longest individual drive was 930 meters and comprised two underground curves with a radius of 450m and 900m. Using the Herrenknecht SLS RV navigation system, the cutterhead was guided with millimeter precision and the task was carried out in a precise and safe manner.

The pipe jacking portion of the project was completed December 14, 2010, and represented a significant milestone for the Warsaw wastewater project.

To complete the entire sewer system and connect it with Czajka wastewater treatment plant (WWTP), a 1,300m long tunnel crossing the Vistula River must be constructed. The project managers have selected a Herrenknecht large diameter tunnel boring machine for the mission.

###

Sponsored Recommendations

ArmorBlock 5000: Boost Automation Efficiency

April 25, 2024
Discover the transformative benefits of leveraging a scalable On-Machine I/O to improve flexibility, enhance reliability and streamline operations.

Rising Cyber Threats and the Impact on Risk and Resiliency Operations

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

State of Smart Manufacturing Report Series

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

SmartSights WIN-911 Alarm Notification Software Enables Faster Response

March 15, 2024
Alarm notification software enables faster response for customers, keeping production on track