The crystalline waterproofing chemistry can be surface-applied on new or cured concrete.
In the form of vapor, water molecules can gradually work their way through the crystal formation and escape out on the downstream side, thus permitting the concrete to dry.
Although crystal formation largely matures in two to three weeks, the process can continue virtually as long as there is water in the concrete. Cessation usually occurs due to natural drying of the concrete. The reaction effectively never runs out of lime, meaning that if water re-enters the concrete years later, it automatically reactivates the waterproofing chemicals. New crystallization begins.
At the micro-level, shrinkage-cracking from drying potentially creates passageways for moisture infiltration. If they occur while crystals are still forming, micro-cracks up to 0.4 mm can be bridged. If they occur later and allow water infiltration, the water reactivates the waterproofing chemicals, making the concrete self-healing on the micro scale.
The crystalline waterproofing technology is non-toxic, contains no VOC’s (volatile organic compounds), and is NSF-61 approved for potable water.
Case Studies
A landmark wastewater treatment plant project is taking place in Miami-Dade County, FL. The plant will serve about a third of Miami-Dade’s 2.5 million residents. Adjacent to Biscayne Bay, the South District WWTP is being upgraded to a high-level disinfection facility with a peak flow capacity of 285 mgd, an increase of 27 percent. It is the largest domestic wastewater injection site, and one of the largest deep bed sand filter plants in the country.
In phase one, over 52,000 square feet of surface area was treated with a two-coat crystalline chemical system manufactured by Xypex Chemical Corp. This was done to waterproof and protect the transfer pump station, flocculation tanks and filters.
Phase 2 also uses the crystalline technology, as an admixture, for waterproofing and protection of an oxygenation train, four new clarifiers, associated splitter boxes and a pump station. An estimated 400,000 lbs. of the Xypex product is required for a substantial portion of 70,000 cubic yards of concrete being poured in place.
“We think it brings value to this project by increasing the concrete’s density,” said John Hoffman, PE, Construction Manager for Phase 2.