In an effort to relieve flooding during the rapid development of the northwest suburbs during the 1960s and 1970’s, the MWRD, the Lake County Forest Preserve District, and the Village of Buffalo Grove entered into an agreement in 1973 to acquire the Buffalo Creek site. The MWRD completed construction on the original reservoir in 1983, including an earthen dam, concrete spillway and 48-inch outlet pipe. A second agreement led to an expansion of the reservoir in 1988, creating the upper pool, as well as modifying the emergency spillway. In 2011, the MWRD published the Lower Des Plaines Detailed Watershed Plan, identifying further expansion of the reservoir to help flood prone areas.
During preliminary engineering, the MWRD developed five different sized reservoir expansion alternatives, and worked with the Army Corps to determine each alternative’s economic benefits. The chosen design utilized an additional 180 acre-feet of storage, which the USACE determined would reduce future flood damages by more than $26 million.
Lake County Grading Company expanded the reservoir before the MWRD established native plantings. Monitoring and maintenance are underway to ensure the survival of native species at the site. Concurrently, MWRD is also monitoring and maintaining the two reaches of stream restoration along the Buffalo Creek Main Stem and the West Unnamed Tributary.