Figure 2: Artist’s rendering of a CULTEC parking lot system. |
Sheamus Kelleher, Operations Manager with Emerald Excavating, agreed: “The site did not have enough space to accommodate a detention pond that would be large enough to handle the volume of stormwater runoff from the added impervious areas.”
The engineers’ solution was a subsurface plastic chamber system from CULTEC.
“Underground chambers are a good option when land availability is an issue,” said Rogers.
The chambers can be used as subsurface retention or detention systems and as replacements for ponds, concrete structures or pipe and stone installations. A variety of chamber sizes accommodate almost any site constraint, and the company’s higher profile Recharger® series makes optimal use of large storage capacities in a smaller footprint.
The engineers replaced about three quarters of the detention pond with 442 units of Recharger 330XL, the model that has a capacity of 7.5 cubic feet per linear foot. This chamber model was used in conjunction with the HVLV™ 180 header units, which have an open bottom to allow for the maximum flow volumes at a retarded rate of speed, similar to the design of the plastic chambers.
The site’s existing and proposed drainage piping needed to be connected to the system at each end and in the middle, so the engineers used the HVLV 180 header system to provide equal flow distribution to the Recharger 330XL chambers. The combined storage capacity of the installed header units and chambers provided 58,000 cubic feet of the required storage.
Specific to Reinhart’s site, the system was located beneath the groundwater level at the same depth as the detention basin. While this positioning allowed the connection of the new system with the existing drainage elements, it also posed a question of meeting the infiltration requirement. In the end, the engineers added a shallow infiltration trench to the underground chamber system. The trench was designed to collect roof runoff, with its overflow discharging into the CULTEC system.
Design Strategies
According to the system’s design, the site runoff is piped to the underground system and surface detention basin, then slowly discharged by the outlet control box to the street swale, causing stormwater to collect and rise in the system to the point where one foot of freeboard remains at the surface basin during a 100-year event.
The engineers used HydroCAD® modeling software to analyze the site and design the system. The program already included the Recharger 330XL parameters, so the engineers only needed to specify the six-inch layers of stone above and below the chambers.