First, decide what the pollutants of concern will be for the site. If gross pollutants such as trash, debris and vegetative trimmings will be prevalent, there should be an element that can trap and hold these types of materials. Because they tend to move in higher flows, this element should remain on-line in all flows. Using something like a wet pond to hold these materials will result in decomposition of the paper and vegetative materials, and subsequent discharge downstream. True suspensions (including bacteria) will obviously not be trapped in an element that depends on settling, such as a manufactured separation vault. Oil and hydrocarbons will require some method of intervention to prevent them from moving downstream. Dissolved chemicals cannot be removed easily (such as salt water) and require a much different type of approach. The elements that treat dissolved chemicals typically need to be protected from sediments, trash and debris. If there is no attention paid to the types of pollutants likely to be generated on the site, there is no possibility of implementing a proper design.
Second, decide which BMPs would address the pollutants of concern and where they should be located. For an isolated source, such as a gas island, perhaps overhead protection from rainfall coupled with a treatment element at one point could stop hydrocarbons before they enter the rest of the system and co-mingle with the rest of the water. For a general source, such as dissolved chemicals, fertilizers and pesticides, perhaps at location downstream of all other BMPs detention might be in order. As a part of the location decision, there should be some consideration given to whether a BMP should stay on-line for all flows or should bypass everything except the defined water quality flow. While it is true that some of the constituents move early in a storm and at low flows (dissolved chemicals and tiny particles), others move only in higher flows or are distributed over a wide range of flows.
Finally, once it's been determined what the pollutants are, and where the proper BMPs should be located, it is important to look at the overall design concept for the site. This is presented here as a final step but it really is the beginning of the process of taking the concepts developed in the first two steps, and implementing them into an actual site design. Physical constraints will dictate some elements of design but there are overreaching principles that should be considered and may dictate changes.
First, look at ways to prevent pollutants from mixing with stormwater in the first place. For example, is it necessary to run relatively clean water from roof drains across a parking lot? Next, look at water quantity control in light of the known pollutants and methods of control. This is essentially how Low Impact Development (LID) is integrated into a site design. Often, elements that control water quantity, such as cisterns, infiltration, or other on-site re-use, will result in better water quality.
Consider this process on the hypothetical gas station/convenience store. We expect hydrocarbons will be spilled in this operation incidentally or perhaps in a large quantity from an accident. High traffic counts will mean a high sediment load, and lots of trash and debris will be encountered. This is not a highly landscaped site, so the threat of excess nutrients is less likely. We know that we can use a spill-trapping BMP and that sediments and trash are easy to address. Now we look at ways to use LID to make everything easier. We take the roof water from the store and put it into a cistern with minimal treatment (it should be pretty clean) to use for irrigation and wash down. This will make every element in the drainage system smaller and will make the flow rates lower. We cover the gas dispensing operation and grade it to prevent water from outside the canopy from running over the area. Now, we can isolate the spill potential and treat it locally before it enters the main drainage flow. We incorporate a trash-screening separator into the system above a wet detention pond so that it does not become impacted with excess sediments, nutrients and trash. This pond and the pipes leading to it are smaller because of the water we have diverted to the cistern. The savings here, as well as the savings generated from not buying water to irrigate the landscape, may help pay for the cistern. Having saved a bit of land by using a smaller pond, perhaps we have room for a small infiltration field (soils permitting) located after the pond. This would use water slowly routed from the pond after all the other forms of treatment and certainly would not be "on-line" for all flows, especially high flow containing hydrocarbons, sediments and debris.
Does this seem like a better approach than picking a standard BMP flat-rated at 80% TSS removal from a manual? Of course it is -- and it might actually be less expensive than the "standard" approach. We have learned much over the past two decades and it is time to put this knowledge to use in our designs in a way that is practical, sustainable, and affordable.