Click here to enlarge imageFive years ago the Marblehead Water and Sewer Commission (MWSC), which serves 20,000 residents, was facing rising insurance claims and repair costs related to system failures and sewer backups of its approximately 87 miles of sewer pipe. By adopting a five-step, systematic approach to Infrastructure Asset Management, or IAM, the town has not only eliminated these problems, but has actually improved both the condition of its assets and its allocation of resources and budget.
Step One: Map Buried Assets
Map Buried Assets In 2003, recognizing the need to document the location and physical attributes of its buried assets, the MWSC hired a consultant to develop an electronic map of its collection system using Geographic Information System (GIS) technology. Existing as-built drawings and records were incorporated into the mapping project, which was completed in 2004. The town now had an electronic reference point and system to document not only the location but also the size, material, year installed and other attributes of its entire collection system.
Step Two: Perform Inventory of Assets
Once mapping was complete, the Water and Sewer Commission hired InfraMetrix LLC to perform an inventory update and structural conditions assessment on a pilot project that contained about 10 miles of pipe and 187 manholes.
Using truck-mounted zoom camera technology, InfraMetrix located and inspected each manhole and pipeline using Pipeline Assessment Certification Program (PACP) techniques. The physical attributes, maintenance requirements, and the condition of all the district's assets were evaluated. Once the condition assessment was completed, InfraMetrix corrected and expanded the GIS to include the zoom camera video inspections, defect photos, and the service and structural condition ratings as determined by their evaluation.
Having proven the value of capturing current inventory and condition assessment on the pilot, the MWSC initiated a second IAM and Risk Assessment project in October 2005.
This time, InfraMetrix's inspection data and observations were loaded into VUEWorks, an Asset Management software solution that provides the MWSC with the ability to query the inspections and videos attached to an asset directly from the GIS map. Updates to the sewer system inventory were automatically reflected in the VUEWorks software.
InfraMetrix inspected 351 manholes and 370 pipe segments in less than four weeks. The manhole inspections revealed that 52% of the inspected manholes had a potential for blockage and 18% were urgent. The service condition of pipelines was similar to the service condition of manholes: 15% of the inspected manholes required immediate attention, while 20% of the inspected manholes were found to need repairs. The pipelines were found to be in very good structural condition.
Step Three: Identify Immediate Capital Needs
Having successfully gone through Steps 1 and 2, the MWSC now had a prioritized list of cleaning and in-line inspection recommendations. Only 5% of the inspected pipelines required more detailed in-line CCTV inspection, providing a significant cost savings than if the Commission had elected to use a traditional in-line CCTV process. Instead, the MWSC could focus its resources in problem areas discovered during the screening process. The MWSC proceeded to clean the manholes and pipelines with immediate potential for blockage issues, which could lead to costly environmental clean-up and property damage settlements.
Step Four: Rank Assets
The next step towards IAM was to assess the probabilities and consequences of asset failure in order to prioritize repairs and capital spending. First, assets were assigned critical attribute data and the importance of each asset was weighted with a consequences-of-failure score based on its impact on the system. For example, a 70-year-old sewer pipe serving 15 households would be weighted less important than a 40-year-old pipe serving 100 households. In this way, MWSC was able to forecast the probability of service and structural failure, calculating risk as the product of the consequence and the probability of failure for each asset. The outcome of this step was a prioritized list of maintenance and capital improvements.