A number of factors persuaded the utility to select Sulzer to complete the work, not least the competitive tender, which was 25 percent below the investment required by the original manufacturer. Furthermore, being able to provide a full turnkey solution to the full equipment and the proximity of a Sulzer service center to the site, as well as the speed in which the work could be completed, were also favorable.
Cutting Lead Times
Sulzer put together the complete lift plan documentation as part of the method statement and risk assessment. The pump had to be partially disassembled and removed in three sections. The service center designed and manufactured a specialist lifting tool that was tested and certified before being used by the field service team to remove the pump from the dry well.
The process was further complicated by the fact that the main shaft, which required replacement, would not come apart and had to be cut in one place to enable removal. Sulzer provided a solution to manufacture a new shaft section after the original equipment manufacturer provided a lead time for a replacement of several months.
The project involved the complete overhaul of the pump and motor assemblies, all of which could be completed at the same location. As a turnkey solution, Sulzer provided field service engineers to arrange the lift and removal of the pump as well as the reinstallation of the full unit including motor, after the refurbishment had been completed.
Corrosion Protection
Once the pump had been disassembled, all the components were inspected and identified for replacement or re-engineering. A considerable amount of corrosion was found on the impeller and the suction sleeves. Sulzer applied a specialist coating on all parts that required additional protection against corrosion to extend the operating life of these components.
During the project, some of the maintenance team from the wastewater treatment plant visited the service center to check on progress and see for themselves the levels of corrosion inside the pump.
Having discovered the full extent of the wear and tear on the pumps after 25 years, the site maintenance team is putting together a plan with Sulzer to refurbish the remaining pumps. This can be achieved without affecting the capacity of the site, with Sulzer providing the engineering and logistics support for a turnkey project.